Project Whare Karakia

Tena koutou whanau,

Project Whare Karakia is in Five stage's;

Stage one- Re piling. - - - - - - - - - - - - - - - - - - - Completed
Stage two- External referbish.
Stage three- Internal referbish.
Stage four- Land Scape entrance way.
Stage five- Recommission Ceremony.

Stage one of our Whare Karakia has been completed.
Whangarei District Council Resourse Consent has been signed off by the engineer.

It is now time to begin stage two and three.

The following list will give you an idea of products that are required.

1. Scafolding
2. Sandpaper
3. Sanding machine's
4. dust masks/coveralls disposable
5. Paint brush's & trays
6. Paint-primer and topcoat, various colours
7. Guttering
8. Spouting
9. Wood putty
10. Paint Striper
11. Timber H3 4x2, 6x2, 8x2 and decking
12. Trades persons

If you can assist with any of the above items please let us know.

And remember.... if you cant make it to this working bee there is going to be 1 held each month so hopefully you can find a date that suits you :)
The dates are as follows:
-June Sat 18th
-July Sat 16th
-August Sat 20th
-September Sat 17th
-October Sat 15th
-November Sat 19th